New type dry process cement technology of our country has passed over 20 years since importing to self-developing, we gradually summarize and innovate, and have gone out of our country. Whatever process design, assembly capability or erection capability has reached international advanced level. However concerning the management of new type dry process cement production, as the development of new type dry process cement process is too fast in domestic market, the enterprise is comparatively slow, so human resources is comparatively lack, meanwhile many enterprises don’t have enough understand of new type dry process cement production, so the manufacturing management, equipment management, quality control is not very scientific and reasonable, especially for the rotary kiln operation in central control room, there are a lot of mistaken ideas, so sometimes they can’t solve the process barrier.
1. Draw up testing method via erection instruction and relevant acceptance rules, prepare testing tool and instrument
2. Draw up testing method and prepare testing tool and instrument via technical requirement and content of basic acceptance
3. Draw up testing method and prepare testing tool and instrument via testing requirement and content of rotary kiln equipment
4. Draw up testing method and prepare testing tool and instrument via correct technical requirement and content of rotary kiln equipment via erection process
5. According to the requirement of construction period and the technical force, equipment capacity of construction enterprise, main content of rotary kiln construction solution is as follows:
6. Introduce the model, type, performance, maximum outline dimension, weight, installed position, position of spare part yard, relative dimension of rotary kiln foundation and related condition of construction site.
7. Confirm and draw the program and construction method of rotary kiln installation.
8. Draw up the form with required tools, machines, testing instrument, fuel and material consumption.
9. Draw up construction schedule according to general plan of the plant.
10. Draw up construction organization and dynamic labor form according to the erection program, construction method and construction schedule.